Description
A new grit classifier is to be installed at Wastewater Treatment Facility No. 2 to replace the current grit classifier which inadequately sized and at a location where grit piping clogging is an on-going issue. The new classifier will be at a different location closer to the grit pumps, allowing for less piping and bends.
Project Information
Contract Award Date (Design): July 2024
Consultant: Quiddity Engineering, LLC
Village: Cochran’s Crossing
MUD: 67
WWTP 2 Grit Classifier Improvements
Status & Schedule
Project Design: August 2024–September 2025
Anticipated Project Start (Construction): December 2025
Dates are subject to change.