Description

A new grit classifier is to be installed at Wastewater Treatment Facility No. 2 to replace the current grit classifier which inadequately sized and at a location where grit piping clogging is an on-going issue.  The new classifier will be at a different location closer to the grit pumps, allowing for less piping and bends.

Map_WWTP2GritClassifierImp

Project Information

Contract Award Date (Design): July 2024

Consultant: Quiddity Engineering, LLC

Village: Cochran’s Crossing

MUD: 67

WWTP 2 Grit Classifier Improvements

Status & Schedule

Project Design: August 2024–September 2025

Anticipated Project Start (Construction): December 2025

Dates are subject to change.