Description
This project consists of relocating approximately 800 linear feet of existing 24-inch water line and fiber optic conduit along State Highway 75 between FM 830 and Silver Springs Road 20’ to the west in a new easement due to widening of the State Highway 75 right-of-way, which encroaches into SJRA’s current easement, water line and fiber optic line alignment.
Project Information
Contract Award Date (Design): July 2025
Consultant: Lockwood, Andrews & Newnam, Inc.
24 inch SJRA GRP Water Line Relocation
Status & Schedule
Project Design: August 2025-April 2026
Anticipated Project Start (Construction): July 2026
Dates are subject to change.