Sanitary Sewer Transmission Assessment and Renewal Program-Phase 1

Description

Extensive flow monitoring of the wholesale sanitary sewer system will be conducted as well as analysis of dry and wet weather flow monitoring and rainfall data, identification of infiltration and inflow locations and sources, conditions assessment, and hydraulic modeling.

Information

Design Consultant: Garver
Contractor: N/A
PDF Map: SSTAR Program

Status & Schedule

Contractor Notice to Proceed: October 2018
Project Completion: Spring 2020
Village: All except Creekside Park
MUDs: All (including MUD 386 in Montgomery County)

Dates are subject to change.