Wastewater Treatment Facility No. 2 Disinfection Improvements

Description

Replacement of disinfection system at wastewater plant.

Information

Design Consultant: Carollo
Contractor: Industrial TX Corp
PDF Map: Wastewater Treatment Facility No. 2 Disinfection Improvements

Status & Schedule

Project Start: October 2017
Project Completion: Spring 2019
Village: Cochran’s Crossing
MUD: MUD 67