South Canal Improvements

Description

Project includes work along a large portion of the SJRA Highlands South Canal which runs south from the SJRA Highlands Reservoir through both Highlands and Baytown, crosses both I-10 and Spur 330/Decker Drive, and terminates at industrial customers.

Information

Contract Award Date: April 2018
Contractor: Lecon, Inc.
PDF Map: South Canal Improvements

Status & Schedule

Contractor Notice to Proceed: May 2017
Anticipated Project Completion: May 2018

Dates are subject to change.

Jones Road/Siphon 28 Detour

Anticipated Jones Road Closure Dates and Duration

August 22, 2017 4 days

Dates are subject to change.